HomeLatestHokkaido Shinkansen Sapporo Extension Delayed by 12 Years

Hokkaido Shinkansen Sapporo Extension Delayed by 12 Years

SAPPORO, Jan 15 (News On Japan) –
The long-delayed extension of the Hokkaido Shinkansen to Sapporo is going through additional setbacks, with the opening now pushed again by greater than a decade and complete mission prices projected to greater than double, at the same time as building steadily advances on the bottom.

Nearly 10 years have handed because the Hokkaido Shinkansen made its high-profile debut, linking Honshu and Hokkaido by means of the Seikan Tunnel in March 2016, when a particular service emerged from the tunnel to mark the arrival of bullet trains on the island.

At the time, the plan envisioned trains operating between Sapporo and Tokyo in 4 hours and 49 minutes inside 5 years, however the Sapporo extension has since been delayed repeatedly and is now anticipated to open no sooner than fiscal 2038.

At the identical time, complete mission prices are forecast to exceed twice the unique estimate, prompting questions on why bills have ballooned and the way the large enterprise is progressing.

East of Sapporo Station, stretching towards Naebo Station, an enormous construction is beneath building that can function a devoted Shinkansen rolling stock depot for Sapporo, a web site {that a} yr in the past held little greater than rows of building automobiles.

For the primary time, tv cameras had been allowed contained in the depot building web site, the place the ability is being constructed on elevated buildings, an association with few precedents nationwide for Shinkansen depots.

Inside an enormous sheltered house, Shinkansen trains will finally be parked, with the realm past set to grow to be JR’s Sapporo Shinkansen Station, whereas a 1,344-meter-long depot will likely be situated on the japanese facet of the station, spanning National Route 5 and Soseigawa-dori.

The depot is designed to accommodate three full practice units facet by facet, with elevated buildings round 60 p.c full as of January 1st, and work now progressing on the slabs that can type the observe mattress for Shinkansen operations, based on officers from the Japan Railway Construction, Transport and Technology Agency.

Once accomplished in about two years, the depot will likely be coated by a protecting shelter to protect in opposition to snow and harsh climate, a form that has already earned it the nickname “an eel’s sleeping quarters” amongst rail fanatics.

The route between Shin-Hakodate-Hokuto and Sapporo spans roughly 212 kilometers, with about 80 p.c operating by means of tunnels, main some to dub it the “mole Shinkansen.”

One of the most important challenges is the Satsutari Tunnel, which cuts beneath Otaru and Sapporo and stretches greater than 26 kilometers, the place excavation continues across the clock, with rock blasted twice a day and carried out by conveyor belts.

From the tunnel entrance in Teine Ward’s Kanayama district, work has superior about 1.2 kilometers towards Otaru, with the tunnel’s primary form largely full regardless of the absence of tracks or rivers at this stage.

Overall progress on the Satsutari Tunnel stands at slightly below 60 p.c, with building now operating about three years behind the unique schedule, as crews reinforce tunnel partitions by inserting bolts at common intervals, permitting excavation to advance by as much as six meters per day.

According to the railway company, excavation has been accomplished in 10 of the 17 tunnels alongside the route, however progress has not been uniform, with main rock formations found in tunnels such because the Yotei Tunnel within the Shiribeshi area, considerably complicating building.

Rising materials costs, larger labor prices, and tighter rules on employees’ hours have additional extended the mission, pushing the estimated complete price from an preliminary 1.67 trillion yen to greater than 3.5 trillion yen within the newest projections.

For native governments, the associated fee improve has introduced recent considerations, significantly in cities like Yakumo, the place a deliberate station tentatively named “Shin-Yakumo Station” will likely be situated about three kilometers from the city middle.

Under the present framework, two-thirds of the development prices excluding JR’s mortgage funds are coated by the nationwide authorities, with the remaining third borne by Hokkaido and municipalities alongside the route.

Yakumo Mayor Toshimi Mantani stated the city had initially anticipated to shoulder round 800 million yen, however that determine is now projected to rise by roughly 400 million yen to about 1.2 billion yen.

While the station is predicted to position Yakumo inside about 50 minutes of Sapporo and instantly join the city to Tokyo, with officers envisioning Japan’s first Shinkansen station “in the middle of a ranch,” the burden of native infrastructure growth, together with water and sewer techniques across the station, is weighing closely on the municipality.

Mantani stated Yakumo and different communities alongside the road plan to induce the nationwide authorities to speed up the mission and scale back native monetary burdens as a lot as attainable.

Among native residents, anticipation and unease coexist, with longtime restaurateur Naoki Shinohara recalling how he created an unique curry impressed by Yakumo a decade in the past, longing for the day the Shinkansen would arrive, solely to see the timeline pushed again once more.

Shinohara stated he nonetheless struggles to reconcile the concept of delays driving cash out of the city, however hopes elevated tourism will finally materialize, including that he desires to remain optimistic regardless of the uncertainty.

As questions persist over whether or not prices will rise additional and whether or not Sapporo can certainly be linked to Tokyo inside the subsequent 12 years, building on the Hokkaido Shinkansen continues amid mounting challenges.

According to broadcasters, the 212-kilometer route between Shin-Hakodate-Hokuto and Sapporo contains 17 tunnels, with estimated journey instances of about 25 minutes to Kutchan, 50 minutes to Yakumo, and round 1 hour and 5 minutes to Shin-Hakodate-Hokuto.

Yakumo, which faces a extreme scarcity of medical doctors, can be hoping that turning into a day-trip distance from Sapporo will make it attainable for physicians to commute, probably easing native healthcare shortages.

Commentators famous that whereas dramatically shorter journey instances might enhance exchanges between areas, the mission’s swelling prices, now exceeding Hokkaido’s annual price range of roughly 3 trillion yen, have elevated the Shinkansen extension into a serious political problem for the area, underscoring the necessity to steadiness comfort, security, and monetary accountability because the mission strikes ahead.

Source: HBCニュース 北海道放送