Damage to Tunnel Boring Machine Halts Tokyo Maglev Work

TOKYO –
Construction of an underground tunnel for Japan’s Linear Chuo Shinkansen in Tokyo’s Shinagawa Ward is anticipated to stay suspended for at the least one other six months after harm was found in a number of parts of a giant tunnel boring machine, in keeping with Central Japan Railway (JR Central).

JR Central halted excavation work in July on the Kita-Shinagawa development part after uncommon noises had been detected coming from the machine throughout underground tunneling operations.

Inspections performed because the suspension have revealed a number of broken parts, together with chipped enamel on gears connecting the machine’s chopping head to its motor.

According to JR Central, additional inspections and investigations are anticipated to take at the least six months, with further time required earlier than excavation work can resume.

The firm stated the suspension isn’t anticipated to have an effect on the deliberate opening schedule of the Linear Chuo Shinkansen, regardless of the prolonged delay to tunneling operations in Shinagawa.

The Linear Chuo Shinkansen undertaking is designed to attach Tokyo and Nagoya utilizing superconducting magnetic levitation expertise, with the Kita-Shinagawa part forming a part of the underground infrastructure being developed for the brand new high-speed railway.